Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "COSMOS i11 QA Phase Execution"
(→QA Test Execution Activities for i11) |
(→QA Test Execution Activities for i11) |
||
Line 10: | Line 10: | ||
* DataVisualization.UI.Component.Widget.testsuite / UI.Reports.testsuite | * DataVisualization.UI.Component.Widget.testsuite / UI.Reports.testsuite | ||
4. Execution of i11 supplement e2e tests (negative) from QA. | 4. Execution of i11 supplement e2e tests (negative) from QA. | ||
− | * http://wiki.eclipse.org/COSMOS_QA_End2End_Tests#End2End_Supplement_Tests_.28Negative.29 | + | * http://wiki.eclipse.org/COSMOS_QA_End2End_Tests#End2End_Supplement_Tests_.28Negative.29 |
5. Eclipse tooling tests - MDR toolkit and SML Tooling (UI tests)() | 5. Eclipse tooling tests - MDR toolkit and SML Tooling (UI tests)() | ||
* org.eclipse.cosmos.me.dmtoolkit.tests/ManagementEnablement.UI.dmtoolkit.testsuite | * org.eclipse.cosmos.me.dmtoolkit.tests/ManagementEnablement.UI.dmtoolkit.testsuite |
Revision as of 02:41, 16 June 2008
QA Test Execution Activities for i11
Primary Tasks:
1. E2E testing on Windows XP, 2003 and Red Hat Enterprise Linux Server 5.0
2. i11 ERs – JUnits/Manual Tests inspection
3. Data Visualization TPTP Manual Tests Execution
- DataVisualization.UI.Component.Widget.testsuite / UI.Reports.testsuite
4. Execution of i11 supplement e2e tests (negative) from QA.
5. Eclipse tooling tests - MDR toolkit and SML Tooling (UI tests)()
- org.eclipse.cosmos.me.dmtoolkit.tests/ManagementEnablement.UI.dmtoolkit.testsuite
- SML Tooling - adhoc UI testing for editor/validator/import/export features
Secondary Tasks:
6. Basic operational efficiency tests (limited performance tests)
For complete i11 QA Activities, refer http://wiki.eclipse.org/COSMOS_QA_i10_Activities