Difference between revisions of "BIRT2.3 Rampdown Policy"
(→Date) |
(→Date) |
||
Line 12: | Line 12: | ||
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update. <br/> | Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update. <br/> | ||
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build. <br/> | Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build. <br/> | ||
+ | |||
+ | |||
+ | '''May 20 : BIRT 2.3 RC1''' | ||
+ | |||
+ | Through May 18, Testing and Fix pass. <br/> | ||
+ | Monday May 19 : BIRT 2.3 RC1 Candidate build <br/> | ||
+ | Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update. <br/> | ||
+ | Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build. <br/> | ||
+ | |||
+ | |||
+ | '''May 27 : BIRT 2.3 RC2''' | ||
+ | |||
+ | Through May 25, Testing and Fix pass. <br/> | ||
+ | Monday May 26 : BIRT 2.3 RC1 Candidate build <br/> | ||
+ | Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update. <br/> | ||
+ | Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC1 and vote for the candidate build. <br/> |
Revision as of 01:12, 8 May 2008
Purpose
This document describes a set of ramp down rules for the BIRT 2.3 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate
Date
May 6 : BIRT 2.3 RCO
Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RCO Candidate build
Monday May 5 until Tuesday May 6: RCO Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.
May 20 : BIRT 2.3 RC1
Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.
May 27 : BIRT 2.3 RC2
Through May 25, Testing and Fix pass.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC1 and vote for the candidate build.