Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "COSMOS Project Plan"
Line 1: | Line 1: | ||
COSMOS RELEASE SCHEDULE FOR 2007 | COSMOS RELEASE SCHEDULE FOR 2007 | ||
+ | |||
+ | Link to Europa Release: http://wiki.eclipse.org/index.php/Europa_Simultaneous_Release | ||
{| style="width:75%; height:100px" border="1" | {| style="width:75%; height:100px" border="1" |
Revision as of 18:12, 23 February 2007
COSMOS RELEASE SCHEDULE FOR 2007
Link to Europa Release: http://wiki.eclipse.org/index.php/Europa_Simultaneous_Release
Milestone/Task | Planned Start | Planned End | Actual Start | Actual End | % Complete | Comments |
---|---|---|---|---|---|---|
Iteration 1-3 definition | 01/01/07 | 03/19/07 | - | - | - | on track |
Iteration 1 demo development | 01/01/07 | 02/23/07 | - | - | - | on track |
Release 1 requirement priority | 03/05/07 | 03/19/07 | - | - | - | on track |
Release vote by community | 03/05/07 | 03/23/07 | - | - | - | on track |
Release 1 plan closure | 03/20/07 | 03/30/07 | - | - | - | on track |
Iteration 2 development and test | 02/23/07 | 04/06/07 | - | - | - | at risk |
Iteration 3 development and test | 04/01/07 | 05/18/07 | - | - | - | - |
Iteration 4 development and test | 05/01/07 | 06/15/07 | - | - | - | - |
Code Freeze | 06/01/07 | 06/23/07 | - | - | - | - |
Europa GA | 06/29/07 | 06/29/07 | - | - | - | to ship alongside |
- Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo)
- Iteration 2: Complete iteration 2 by 4/16. (need i2 plan)
- Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa.