Swordfish Documentation: Sprint Plan
Revision as of 15:19, 29 March 2009 by Unnamed Poltroon (Talk)
{{#eclipseproject:rt.swordfish}}
Swordfish Sprints for Galileo
Update 27.03.2009: Merged sprints 4 and 5:
- Fr. 03.04: Sprint 3 Demo, Retrospective + Feature Estimates
- Mo. 06.04: Sprint 4 Planung
- Tue. 07.04 until incl. Mi. 29.04: Sprint 4 development
- Mo. 20.04: Checkpoint: All mandatory M7 requirements fulfilled?
- Thu. 30.04: Sprint 4 Demo
Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project. The Features and Tasks for Each sprint can be accessed through the links below:
sprint1: 09.02.2009 – 05.03.2009
sprint2: 06.03.2009 – 18.03.2009 (M6)
sprint3: 19.03.2009 – 02.04.2009
sprint4: 03.04.2009 – 16.04.2009
sprint5: 17.04.2009 – 06.05.2009 (M7)
sprint6: 07.05.2009 – 20.05.2009 (RC1)
Release: 21.05.2009 – 17.06.2009 (Endgame)