Difference between revisions of "COSMOS ME Minutes 15JUL08"
(New page: == Logistics == * Date: 15JUL08 * Time: 11AM EST * Attendees: Brad Beck, Merri Jensen, Jeff Hamm, Robert DeMason, Jason Losh, Eric Rose, Chris Mildebrant, Julia McCarthy, Yan Zhao, Josh He...) |
|||
Line 3: | Line 3: | ||
* Time: 11AM EST | * Time: 11AM EST | ||
* Attendees: Brad Beck, Merri Jensen, Jeff Hamm, Robert DeMason, Jason Losh, Eric Rose, Chris Mildebrant, Julia McCarthy, Yan Zhao, Josh Hester, David Whiteman, Charlie Halloran | * Attendees: Brad Beck, Merri Jensen, Jeff Hamm, Robert DeMason, Jason Losh, Eric Rose, Chris Mildebrant, Julia McCarthy, Yan Zhao, Josh Hester, David Whiteman, Charlie Halloran | ||
+ | |||
+ | == Minutes == | ||
+ | |||
+ | # i12 status review | ||
+ | # P2 alignment work is ongoing | ||
+ | #* The team believes there us much in P2 we can use. Jeff/Jason/Merri/Mark have been reviewing P2 and stepping through its function. There is a lot of concepts and core components that map directly to the SDD runtime design. | ||
+ | # Tooling work is progressing | ||
+ | #* BTG work will be slowed a bit. Josh/Robert will be proceeding with BTG work in the interim. | ||
+ | #* Tuscany needs to be removed from the CA. Jason has asked Merri to look into this. | ||
+ | # SML/SDD alignment discussion | ||
+ | #* Julia to discuss in 2-3 weeks and ping Jason as to the target date of the meeting so the agenda can be set for that discussion. |
Latest revision as of 17:25, 21 July 2008
Logistics
- Date: 15JUL08
- Time: 11AM EST
- Attendees: Brad Beck, Merri Jensen, Jeff Hamm, Robert DeMason, Jason Losh, Eric Rose, Chris Mildebrant, Julia McCarthy, Yan Zhao, Josh Hester, David Whiteman, Charlie Halloran
Minutes
- i12 status review
- P2 alignment work is ongoing
- The team believes there us much in P2 we can use. Jeff/Jason/Merri/Mark have been reviewing P2 and stepping through its function. There is a lot of concepts and core components that map directly to the SDD runtime design.
- Tooling work is progressing
- BTG work will be slowed a bit. Josh/Robert will be proceeding with BTG work in the interim.
- Tuscany needs to be removed from the CA. Jason has asked Merri to look into this.
- SML/SDD alignment discussion
- Julia to discuss in 2-3 weeks and ping Jason as to the target date of the meeting so the agenda can be set for that discussion.