Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "Swordfish Documentaion: Sprint Plan"

Line 5: Line 5:
 
Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project.
 
Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project.
  
[[Swordfish_Documentation:_Galileo_Sprint1 | sprint1: 09.02.2009 – 05.03.2009]]  
+
[[Swordfis_Documentation:_Galileo_Sprint1 | sprint1: 09.02.2009 – 05.03.2009]]  
  
 
sprint2: 06.03.2009 – 18.03.2009 (M6)
 
sprint2: 06.03.2009 – 18.03.2009 (M6)

Revision as of 10:32, 9 February 2009

{{#eclipseproject:rt.swordfish}}

Swordfish Sprints for Galileo

Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project.

sprint1: 09.02.2009 – 05.03.2009

sprint2: 06.03.2009 – 18.03.2009 (M6)

sprint3: 19.03.2009 – 02.04.2009

sprint4: 03.04.2009 – 16.04.2009

sprint5: 17.04.2009 – 06.05.2009 (M7)

sprint6: 07.05.2009 – 20.05.2009 (RC1)

Release: 21.05.2009 – 17.06.2009 (Endgame)