Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project.
sprint1: 09.02.2009 – 05.03.2009
sprint2: 06.03.2009 – 18.03.2009 (M6)
sprint3: 19.03.2009 – 02.04.2009
sprint4: 03.04.2009 – 16.04.2009
sprint5: 17.04.2009 – 06.05.2009 (M7)
sprint6: 07.05.2009 – 20.05.2009 (RC1)
Release: 21.05.2009 – 17.06.2009 (Endgame)