Swordfish Documentaion: Sprint Plan

{{#eclipseproject:rt.swordfish}}

Swordfish Sprints for Galileo

Swordfish is developed using the scrum method. For the Galileo release the following sprints have been scheduled in synchronization with the Galileo Milestones for the Swordfish project.

sprint1: 09.02.2009 – 05.03.2009

sprint2: 06.03.2009 – 18.03.2009 (M6)

sprint3: 19.03.2009 – 02.04.2009

sprint4: 03.04.2009 – 16.04.2009

sprint5: 17.04.2009 – 06.05.2009 (M7)

sprint6: 07.05.2009 – 20.05.2009 (RC1)

Release: 21.05.2009 – 17.06.2009 (Endgame)